• Bid Recap      
           
    Contractor Bid Contingency Award
    Amount (10%) Total
    Nata Construction, Inc. $98,500.00 $9,850.00 $108,350.00
    GDL Best Contractor, Inc.  $267,300.00 $29,700.00 $297,000.00
           

     *Apparent Low Bidder: Nata Contruction, Inc.

    The El Monte Union High School District is soliciting bids for the above-referenced project.

    Football Stadium  Bleacher Repair Project - Mountain View  High School CUPCCAA Informal Bid No. 2019-20(B4)

    PROJECT ESTIMATE: $175,000

    PROJECT START DATE: August 1, 2019

    REQUIRED LICENSE: “B” – General Contractor

    PRE-BID/JOB WALK: MANDATORY.

    Date: Monday July 1, 2019, at 8:30a.m.

    Location: Mountain View High School, 2900 Parkway Dr., 91732, Prospective Bidders should arrive 15 minutes early to allow for parking and time to sign-in.

    RFI DEADLINE: Tuesday July 2, 2019, at 12:00 p.m.(PST)

    RFI’s must be submitted in writing and via email only to Claudia Sanchez, Director of Purchasing, at claudia.sanchez@emuhsd.org. No phone calls will be accepted.

    BID SUBMISSION DATE: July 12, 2019, at 10:00 a.m.(PST)

    Late submissions will be rejected and returned unopened